Great news from the Achante project! The structural phase is reaching its final stages, and this week, the roof floor and water tanker slab concrete work are 100% completed.

Key Highlights:

  • Major Milestone: Roof floor and terrace structure work is completely finished.
  • Finishing Works: External plastering is already at 60%, while internal blockwork, electrical piping, and gypsum works are moving forward quickly on multiple floors.

We are keeping our promise with real progress every single day. Watch the full video to see how the site looks right now.

Construction
Milestones

Witness the transformation of our vision into reality. Every phase undergoes rigorous quality checks to ensure superior results matching international standards.

Quality Assurance

Rigorous inspection at every level.

Completed

Structural Phase

Roof floor and water tanker slab concrete work 100% completed.

Current Status

Finishing Works

External plastering 60%, internal blockwork and MEP ongoing.

Final Delivery

Painting, fixtures, and handover preparations.

×